Confidential Thermal Oxidizer Site Shutdown

Delivery
Project & Program Services
Duration
13 months
Project Value
$30 million
Sector

Biotechnology and Pharmaceuticals

CSM Group successfully planned and monitored over 130 tradespeople from 15 companies to execute 18 interdependent projects.

The project was executed during a 22-day TOX system shutdown (including site-wide nitrogen and industrial water), requiring extensive planning and preparation from the team.

Measures such as a temporary TOX system, extensive pre-work, pre-verifications, pre-installations, and a 24/7 work schedule mitigated downtime, allowing site operations to be minimally impacted.

Planning began well before work on the ground to ensure sufficient labor resources were in place to complete the project safely and on time. This included resource graphing and tracking across projects site-wide.

Safety professionals were tracked and assisted with air monitoring, LOTO, safe work permits, and monitoring working conditions throughout the entire process. During this process, an extensive upgrade was made to outdated electrical control systems from a PCL to a DCS to meet the new site standard of Delta V.

To house this new control room, a small building expansion took place with extensive coordination around existing infrastructure, including natural gas, nitrogen, industrial water and storm sewer.

READY TO DISCUSS YOUR PROJECT?

Every project is unique, and so is our approach. We are more than just construction managers; we are your strategic partners. Contact CSM Group today to learn how our tailored solutions can bring your project to life.

Foundry-Featured-Project-Section
"When you head on out to the Moon, in very short order, and you get a chance to look back at the Earth, that horizon slowly curves around in upon himself, and all of sudden you are looking at something that is very strange, but yet is very, very familiar, because you are beginning to see the Earth evolve."
Gene CernanAstronaut, Apollo 17